Expansion of the Goświnowice Ethanol Production Plant
Agreement term: 01.12.2018 - 14.10.2019
SCope of work
- The task was carried out on the basis of several stages and included the delivery of:
- 5 columns
- 4 evaporators
- 2 absorbers
- 2 tanks
As well as assembly and prefabrication of pipelines (C.S. and S.S), a total of 260 tons
The completed facilities were commissioned under our supervision.