Process Installations - PMG Wierzchowice
Scope of work
Turn-Key Execution of 7 Process Installations for Underground Gas Storage (UGS) Wierzchowice - Stage I:- Nitrogen Station (Unit 920)
- Methanol & Biocyd Injection Unit (Unit 950)
- Formation Water Injection Unit (Unit 960)
- Vent Stack (Unit 980)
- Drainage Unit (Unit 990)
- Formation Water Degassing Unit (Unit 880)
- Drainage Degassing Unit (Unit 890)
Scope of work
- Mechanical Design
- Fabrication of 7 turn-key Installations (process tanks, storage tanks, piping systems, structural steel, supports, etc.) in Izotechnik’s premises in Płock/Poland
- Erection of all 7 Installations at site
- Selection, Purchase & Installation of I&C Equipment for all 7 Installations
- Selection, Purchase & Installation of Electrical Equipment for all 7 Installations
- Insulation & Corrosion Protection
- CE-marking
- Final Acceptance Tests of all 7 Installations
- Start-up assistance of all 7 Installations
Materials
SS – 304,
316L,
CS – P265GH,
P275NL1,
L360NB,
L290NB
Working pressure
2 ÷ 350 bar